Witnessing and handover packs that survive the first year
Most BMS projects are judged on the day the witness signs. The building is judged over the year that follows. A system that passed every test in November can be fighting its own heating in May, and by then the engineer who knew why the setpoints are what they are has moved to the next job. What survives is whatever was written down.
This article follows on from Commissioning a BMS. It is for integrators finishing projects, and for the clients, consultants and FM teams who will live with what they hand over. It covers witnessing that proves something, the formal notices and log book in England, and the seasonal visits and aftercare that turn a handover pack into something people still use.
Witnessing is not your first test
Witnessing is the step where someone independent of the installer sees the results checked against the design and the commissioning specification. The contract or commissioning plan should name that person or firm - often the consultant, a client's representative or an independent specialist - and say what they will see and the notice they expect.
BSRIA's Commissioning Responsibilities Framework (BG 88/2025) exists to make those roles explicit, task by task, and it is aligned with CIBSE's Commissioning Code M (2022). Approved Document L points to Code M too, both for the competence of a commissioning manager on large or complex projects and for how commissioning should be carried out (Approved Document L Volume 2, 2026 edition, 7.3 and 7.6).
What makes a witnessing visit worth everyone's time:
- Your own tests are done. Invite the witness when your sensor checks against a reference (see Measurement you can defend), point-to-point checks, the air and water results and a full run of the sequences have already passed - not to find out whether they will.
- A script from the control description. Every line sets out what is done, what should happen, what did happen, and whether it passed. Whether every item or a sample is witnessed is for the specification or the client to say; if sampling, agree who picks the items.
- The real system, not a staged one. Clear the overrides first, and only force a value where the script asks for it and notes it. Safety controls stay in place for the witness exactly as for your own team, and fire interfaces are witnessed against the cause and effect by those appointed to test them (see Smoke control and fire interfaces).
- Honest failures. A failure goes on the issue log, gets fixed and is retested. Then ask which other items could fail for the same reason. Both parties sign and date the results.
A signed witness sheet shows the results were seen. Taking the system into maintenance is a separate step, and the contract says when it happens.
The commissioning notice
In England the Building Regulations require a notice confirming that fixed building services were commissioned according to the approved procedures. Under the 2026 edition of Approved Document L, which takes effect on 24 March 2027, the notice goes to the building control body and the building owner and confirms three things: the commissioning plan was followed, every system was inspected in a suitable sequence and to a reasonable standard, and test results show performance reasonably in line with the design - with written commentary wherever a service does not perform as well as intended (7.7).
The timing depends on the route (7.8). With a local authority building notice or full plans application, the notice is due within five days of commissioning being completed; with a registered building control approver, generally within five days of the work being completed; for higher-risk building work needing a completion certificate, it goes to the regulator with that application; and in other cases, such as competent person scheme work, within 30 days. Until 24 March 2027 most projects work to the 2021 edition, where the same notice sits in Section 8 (Approved Document L Volume 2, 2021 edition incorporating 2023 amendments). Check which edition your project is under.
The "written commentary" line is worth taking seriously. A controls contractor who records honestly that, say, cooling could not be proved in a November handover has protected the client and themselves.
The log book and what goes in it
Regulation 40 requires the person carrying out the work to give the owner, within five days of completion, enough information about the building, its fixed services and their maintenance for it to be run without using more fuel and power than is reasonable. The 2026 edition asks for operating and maintenance instructions in a building log book, which may draw on the O&M manuals or the health and safety file, and points to BSRIA's BG 26/2011 for further advice (8.1). The 2021 edition pointed to CIBSE TM31 instead (9.1-9.2).
The log book should include a copy of the completed commissioning records (8.2). Where building automation and control systems are installed in a new building, information about their energy performance should also go to the owner (8.5; 9.6 in the 2021 edition).
For the controls, a handover pack that someone can actually use usually holds:
- The final control description and points schedule - as running, not as tendered.
- Every setting that matters - setpoints, limits, loop settings, schedules, alarm thresholds - with a note of why any departs from the design.
- Backups of every controller and the front end, dated, and the software versions.
- Signed test and witnessing records, the issue log with its closures, and a list of anything not yet proved.
- Credentials handed securely to a named client contact, never left in the O&M manual.
The first year
Testing in one season cannot prove everything. A building commissioned in winter has not yet cooled anything in anger, and one handed over in summer has not met its first frost. Seasonal commissioning goes back once occupied, as the weather changes, to check heating in winter and cooling in summer; BSRIA publishes guidance on it as BG 44/2013 (BSRIA publications).
BSRIA's Soft Landings Framework (BG 54/2018) sets out a six-phase approach that runs past handover into aftercare, with a full programme of post-occupancy evaluation available. Extended aftercare is commonly described as lasting up to three years after handover, with seasonal tuning and monitoring along the way (Designing Buildings - extended aftercare); what the client agrees sets the real period.
For the integrator, the practical points are:
- Book the return visits at handover, against the list of what could not be proved.
- Use the trends. Faults, comfort complaints and energy use in the first months show what needs adjusting far better than a checklist does.
- Log every change. Each adjustment goes into the log book or change record with a date and a reason. Otherwise the next engineer is working from settings that no longer exist.
- Watch for fit-out. A tenant fit-out that moves partitions or grilles can undo a balance and a control strategy in a week.
Packs that survive
The handover packs that are still useful a year later have three things in common: they describe the system as it runs, they say honestly what was not proved, and they are kept up to date by whoever changes the system next. That last point is a service contract question as much as a commissioning one - which is where Selling BMS service and The BMS service visit pick up.
Sources mentioned: BSRIA BG 88/2025 Commissioning Responsibilities Framework; CIBSE Commissioning Code M (2022); Approved Document L Volume 2, 2026 edition (Sections 7 and 8) and 2021 edition incorporating 2023 amendments (Sections 8 and 9); the Building Regulations 2010, regulations 40 and 44; BSRIA BG 54/2018 Soft Landings Framework and BG 44/2013 Seasonal Commissioning (cited by subject); Designing Buildings on extended aftercare. Wales, Scotland and Northern Ireland have their own rules.
More info
- Commissioning good practice - a tecTraining course
- Air system balancing - a tecTraining course
- AHU commissioning - a tecTraining course
Sign in to go straight to the lessons.
Try the tool
- Commissioning sheets - in tecTools