Commissioning a BMS - a practical sequence and the faults to look for

Commissioning is where a controls installation proves it does what the design said it would. Done in the right order it is calm and predictable; done out of order it turns into days of chasing faults that were really someone else's unfinished work. This article sets out a sequence many integrators follow, the checks at each stage, and the faults that come up again and again. Your project specification and commissioning plan always come first - treat this as a checklist to compare against, not a replacement for them.

Before you start

Most commissioning delays are caused before the controls engineer arrives. It is worth confirming a few things in writing before booking days on site:

Stage 1 - panels and power

Start with the panels de-energised. Check the panel against its drawings, labelling and terminations, then the supplies once it is safe to power up: control transformers, 24 V AC and DC rails, fusing and earthing. Electrical testing must follow your company's safe systems of work and be carried out by people competent to do it. Note any damage or missing items before you go further - it saves arguments later.

Stage 2 - point-to-point checks

Every input and output is proved from the field device back to the controller and on to the head end. This is the stage that is most often rushed and the one that causes the most trouble when it is.

Record every point as you go. A point-to-point sheet signed off point by point is far easier to defend than a ticked box at the end.

Stage 3 - networks and integration

Once the local I/O is proved, bring up the networks. Check controller addressing, device instances and network numbers, baud rates and terminations on serial buses, and IP settings on Ethernet. For third-party plant - chillers, boilers, meters, variable speed drives - confirm the points you read and write against the manufacturer's documentation, including units, scaling and which values are writable. Then pull a cable or power down a device and make sure a communications-loss alarm actually appears.

Stage 4 - control loops and sequences

With the points and networks proved, test the logic against the strategy, one system at a time.

Stage 5 - alarms, trends, schedules and graphics

Operators judge a BMS by what they see, so this stage matters more than it looks. Check that every alarm has a sensible priority, text an operator understands and a route to the right person. Set up trends that will help with the first season's fine-tuning. Load the agreed occupancy schedules and holidays. Walk through the graphics against the plant and make sure values, units and commands are all live and in the right place.

Stage 6 - witnessing and handover

Demonstrate the systems to the client or their representative against the commissioning plan, and keep the signed records. Handover usually includes as-built drawings and points lists, the final strategy, backups of every controller and the head end, user accounts with sensible permissions, and operator training. Plan a return visit: many systems only show their faults in the first change of season, and seasonal commissioning is where a good job becomes a good building.

Faults that come up again and again

Further reading

Published guidance covers this in far more depth. In the UK, the CIBSE Commissioning Codes - in particular Code C for automatic controls and Code M for commissioning management - and BSRIA's commissioning guides are widely referenced in specifications, and Part L of the Building Regulations expects fixed building services to be commissioned and the results notified. Check which documents and editions your specification names, and use those.

If you are building up your own commissioning knowledge, our tecTraining courses include commissioning good practice with a quiz and certificate, and tecTools has commissioning sheets and I/O schedules you can fill in on site.