Which HTM governs which BMS point
An integrator walking into a hospital plant room for the first time meets the same BMS hardware as anywhere else - outstations, sensors, actuators, a head end. What is different is that many of those points sit inside a framework of Health Technical Memoranda (HTMs), each with its own duty holders, and changing them is not a matter of agreeing it with the estates officer on the day.
There is no current, maintained HTM devoted only to building management systems. The BMS duties are spread across several memoranda. This article maps the common hospital BMS points to the HTM that governs them and to the people who must be involved, so an integrator can plan a service visit or an optimisation project without stepping outside the governance. It describes the documents in our own words; always work from the current editions on NHS England's HTM index and the trust's own policies.
The roles that recur
Each HTM uses a similar chain of responsibility, and the same names come up whichever system you touch:
- Designated Person - the board-level person accountable for the system's safety.
- Authorising Engineer (AE) - an independent adviser, appointed by the Designated Person, who audits and advises. There are AEs for ventilation, water, electrical systems and others.
- Authorised Person (AP) - manages the system day to day, issues permits and controls who works on it.
- Competent Person (CP) - carries out the work. An integrator's engineer is usually a Competent Person working under the AP's permit.
On top of the individuals sit multidisciplinary groups - the Ventilation Safety Group and the Water Safety Group in particular - which approve changes to critical systems. An integrator should know, before the first visit, who the AP is for each system on the job list and how permits are issued.
Ventilation points - HTM 03-01
HTM 03-01 covers specialised ventilation in healthcare premises, with Part A on design and Part B on operation (2021 edition). The BMS points it governs include:
- theatre and anaesthetic room AHUs - fan status, airflow or pressure, supply temperature and humidity, filter differential pressure;
- room pressure differentials and the pressure cascade between theatre, anaesthetic room, prep and corridor;
- ultra-clean ventilation canopies and their interlocks;
- isolation rooms, critical care and aseptic pharmacy ventilation;
- heat recovery on those systems, and the interlocks with anaesthetic gas scavenging.
HTM 03-01 names theatres, isolation facilities, critical care and aseptic pharmacy among the systems that need annual verification. Any change to schedules, setpoints, pressure regimes or interlocks on those systems goes through the Ventilation Safety Group and the Authorised Person (Ventilation).
In July 2026 NHS England issued NETB 2026/1, a bulletin supplementing HTM 03-01 that asks trusts to set back or switch off theatre ventilation out of hours. Theatre ventilation setback under NETB 2026/1 covers the BMS side of that work.
Water points - HTM 04-01
HTM 04-01 covers safe water in healthcare premises, in several parts, with Part B on operational management. HSE's main legionella control is temperature, with hot water stored at 60°C or above (HSE). BMS points that fall under the water safety regime include:
- calorifier flow and return temperatures, and pasteurisation cycles;
- hot water return temperatures across the distribution system;
- sentinel outlet temperature sensors, where fitted;
- cold water storage temperatures and booster sets;
- thermostatic mixing valve monitoring, where the BMS sees it.
These are safety points before they are energy points. Lowering a hot water setpoint, changing a pasteurisation schedule or altering sentinel alarm limits is a decision for the Water Safety Group and the Authorised Person (Water), with the AE (Water) advising - never something to adjust during an energy visit. Logging these temperatures reliably, with sensible alarms, is often the most valued thing a BMS does for a water safety group.
Electrical points - HTM 06-01
HTM 06-01 covers electrical services supply and distribution. The BMS usually monitors rather than controls here, but the points matter:
- generator run, fault and fuel level signals, and changeover status;
- UPS and essential supply alarms;
- mains failure and restoration, and how plant restarts afterwards.
The last one is where the BMS has a real job. Plant that restarts all at once on restoration of supply can overload the essential supply or trip, and critical ventilation must come back in the right order. Restart sequencing should be agreed with the electrical AP and tested, not assumed. Any work in switchrooms or on essential supplies is under the electrical permit regime.
Energy and metering - HTM 07-02
HTM 07-02 (EnCO2de, 2015) covers energy and carbon management, including metering, monitoring and targeting. A revision was under consultation in 2024, so check the current edition. The BMS points that support it include:
- main and sub-meters - electricity, gas, heat and water - and their pulse or bus connections;
- the meter hierarchy, so sub-meters reconcile with the main meter;
- out-of-hours profiles and plant run hours.
This is where most optimisation evidence comes from. A trust working towards the NHS target of an 80% cut in direct emissions by 2032 needs metering it can trust, and an integrator who can show reconciled sub-metering, trend history and before-and-after profiles is giving the energy manager exactly what they need. Proving savings covers the method.
Medical gases and other boundaries
The BMS commonly carries alarm signals from medical gas plant, but medical gas systems sit under their own HTM and permit regime, and the BMS does not control them. Treat those points as monitoring only, and never change their alarm handling without the medical gas AP. Fire and smoke control is another boundary: the BMS may receive fire signals and shut down plant, but the fire strategy owns those actions.
What about HTM 2005?
Older references describe HTM 2005 as the memorandum for building management systems, and it is sometimes cited as a model for BMS maintenance. It does not appear in NHS England's current HTM index, and its status is unclear. It may still be useful background on structure, but duties should be cited from the live HTMs above. In Scotland and Wales, check the SHTM and WHTM equivalents, which differ in places.
Putting the map to use
Before a hospital service visit or optimisation survey:
1. List the systems on the job and mark each with its HTM. 2. Name the AP for each system and agree how permits will be issued. 3. Separate monitoring from control. Points the BMS only watches need checking and calibrating; points it controls need governance before any change. 4. Agree the change route. Anything on a critical system goes through the relevant safety group with a written proposal, test plan and back-out. 5. Record evidence. Calibration results, alarm tests and before-and-after trends, filed so the AE can audit them.
The same discipline applies to remote access. NHS clients increasingly ask for evidence of how BMS connections are controlled - see BMS cyber hygiene evidence. For hospital decarbonisation more broadly, see BMS before heat pumps. The BMS health check covers the general survey method, and Alarm rationalisation helps where years of added alarms have buried the important ones.
Related tools and training: the legionella setpoint checker, BMS health check and alarm load worksheet are in tecTools, and the Servicing and optimising an existing BMS course is in tecTraining.
Guidance mentioned: NHS England Health Technical Memoranda 03-01 (2021), 04-01, 06-01 and 07-02 (2015, under revision); NETB 2026/1 (July 2026); HSE guidance on legionella in health services. Always work from the current editions and the trust's own policies - this article is a map, not a substitute for them.