Frost, safeties and the first cold night - what to prove on an AHU before winter
The first properly cold night of the winter finds every weakness in an air handling unit's frost protection. By morning the call has come in: the AHU has tripped on frost, the offices are cold, and someone wants to know why the BMS let it happen - or why it will not reset. Some of those trips are the protection doing exactly its job. Others are a wrong setting, a damper that leaks, a valve that never reached full open, or a device that was bridged out years ago and forgotten.
This article is for integrators and service engineers who look after AHUs, and for the FM teams who take the calls. It covers what frost protection is for, the two different jobs it does, and what a controls engineer should prove before winter. It does not tell you what setting to use or what action the plant should take - those come from the design, the AHU maker and the control description.
Two jobs that get mixed up
Coil frost protection stops the water in a heating or preheat coil from freezing and splitting the tubes. A frozen coil is expensive, it floods the AHU when it thaws, and the unit is out of service while it is replaced.
Heat recovery defrost keeps a plate exchanger, wheel or run-around coil working when moisture in the extract air freezes on the cold side. Ice blocks the passages, pressure drop rises and recovery falls away. Heat recovery that recovers covers the three kinds of exchanger.
They use different sensors and take different actions, and they are often confused on drawings and in alarm text. Approved Document L asks for defrost control on heat exchangers, and for a way to stop, modulate or bypass recovery when it is not wanted, in paragraph 5.60 of the 2026 edition of Volume 2 (6.56 in the 2021 edition). For how either job is done, much of the published detail comes from Eurovent Recommendation 6/17, which is European industry guidance rather than a UK requirement.
How a coil frost scheme usually works
A common arrangement uses a temperature sensor or an air-side frost thermostat close to the coil, and acts in stages as the air temperature falls:
- Stage 1 - heat. The preheat or frost coil valve is driven fully open and its pump is proven running, to put heat into the coil before anything freezes.
- Stage 2 - stop. If the temperature keeps falling, the fans stop and the fresh-air damper closes, so cold air stops being drawn across the coil. A frost alarm goes to the BMS.
- Reset. On many schemes a hard-wired trip needs a deliberate manual reset, so someone looks at the plant before it restarts. How such a trip sits in the panel's safety chain is covered in Hand/Off/Auto, safety chains and the BMS enable.
Sources differ on the detail. Eurovent describes an air-side thermostat with its sensing element downstream of the coil, stopping airflow below the limit, and starting the fans in a cold start only once the heater is at full output. Some North American practice puts the element upstream and adds damper and valve actions; the freeze protection sequence in ASHRAE Guideline 36, as published in the Modelica Buildings Library documentation, stages software action before a shutdown. UK healthcare guidance sets out the valve split - the frost coil's valve goes open on a frost trip, while other heater valves close on airflow or fan failure - in HTM 03-01 Part A, paragraphs 9.212 and 9.223. Where the design and the product instructions disagree, raise a query rather than choosing one.
Heat recovery defrost - and its price
For a heat exchanger, the question is when freezing will start. Outside air temperature is the simplest trigger, but real freezing depends on how moist the extract is, so early defrost wastes energy and late defrost lets ice build. Better schemes look at the exhaust temperature at the critical point, extract humidity, or the pressure drop across the exchanger.
Every defrost action costs something. Preheating costs heat. Bypassing a plate puts load on the heater. Slowing a wheel loses recovery. Cutting the supply fan while the extract runs can pull the building into negative pressure. Which trade-off is right is a design decision. The controls engineer's job is to prove that the chosen action happens when it should - and that it stops again afterwards.
What to prove before winter
The order of proving safeties - wiring checked, then devices operated with fans off, then with fans running at low speed - follows published practice such as CIBSE Commissioning Code C. Work under your method statement, with someone in charge of any override, and log it.
- Detection. The device or sensor is where the drawing says, the setting matches the design, and it responds when tested by the maker's method. No public test method was found for frost thermostats, so follow the product instructions - never improvise with sprays or force.
- Action. On a trip, the valve goes to the position the design gives, the pump runs, the fans stop and the dampers close as written. Watch the plant, not the graphic.
- Alarm. The BMS shows the right alarm text, at the right priority, to the right person, with any delay as specified.
- Reset. The reset is the type the design asks for, it works, and the plant does not restart on its own unless the control description says it should. On a two-stage scheme, check that stage 1 holds the valve open until the higher threshold is regained, not just that it opens.
- Cold start. Where the coil is preheated before the fans run, the preheat time must be longer than the valve actuator's full stroke. A short preheat on a slow actuator means the fans start with the valve only part open.
- Heat recovery defrost. Offset the controlling sensor safely and in the log, see the defrost action and its end, then restore the sensor.
- Nothing left bridged. Every override and link comes off before you leave, and the log says so.
What stays outside the controls engineer's remit: choosing the method, changing a setting, or leaving a frost device overridden to stop nuisance trips.
When it trips anyway
A frost alarm that repeats is telling you something about the plant, not only the device. The usual suspects:
- fresh-air dampers that leak cold air across the coil while the plant is off;
- a cold start with too short a preheat, or none;
- the heat supply not there - boilers locked out, a pump failed, a heating lockout still at its summer value;
- a valve or actuator that sticks, or a valve barely open at low demand, so cold spots form in the coil;
- stratified air, where a cold layer from the fresh-air inlet sits across part of the coil face.
Trend the off-coil temperature, valve position, pump status, damper position and outside air temperature through the first cold fortnight. A trip that comes at the same time every morning is usually a start-up sequence; one that comes on the coldest night alone may be the protection doing its job. Psychrometrics helps check what the air is doing across the coil.
Make it part of autumn readiness
Frost protection belongs on the autumn visit, with pump exercise, heating lockouts, compensation curves and summer overrides - see Seasonal changeover for the full list and The BMS service visit for where it sits in the year.
Sources mentioned: Approved Document L, Volume 2, 2026 edition paragraph 5.60 and 2021 edition paragraph 6.56; Eurovent Recommendation 6/17 (2021), sections 4.4 and 5.3.1 (European industry guidance); ASHRAE Guideline 36 freeze protection as documented in the Modelica Buildings Library; HTM 03-01 Part A (NHS England, 2021), paragraphs 9.212 and 9.223; CIBSE Commissioning Code C (2001). Settings and actions here are examples - the design, the AHU maker's instructions and the control description decide.
More info
- AHU variants - a tecTraining course
- AHU commissioning - a tecTraining course
- Seasonal commissioning and changeover - a tecTraining course
Sign in to go straight to the lessons.
Try the tool
- AHU spot-readings check - in tecTools
- Psychrometrics - in tecTools
- Seasonal changeover - in tecTools