Seasonal changeover - getting a building from heating to cooling, and back

Twice a year, almost every building with a BMS has to change its mind. In spring it stops being a heating building and becomes a cooling building; in autumn it goes back again. The controls strategy usually handles this automatically, but only if the settings, interlocks and plant behind it are still right. Changeover is where faults that hid all season show themselves, and where a short, well-timed visit pays off.

This guide is for systems integrators and controls engineers planning spring and autumn visits on existing buildings. It describes common practice and the published guidance behind it. Your client's strategy, maintenance standard and plant manufacturers' instructions always come first.

What actually changes at changeover

On paper the change is simple: heating demand falls and cooling demand rises, or the other way round. In the BMS, a surprising number of things move with it:

Every one of these is a chance for the building to start the season in the wrong state. The most common changeover complaint - "it is too hot" in a warm April week, or "the heating is not on" on the first cold morning in October - nearly always traces back to one of them.

The spring checklist

Spring changeover is about proving cooling before the building needs it. The aim is to finish before the first warm week, not during it.

The autumn checklist

Autumn readiness is about protecting the plant and the building before the first frost, and getting the heating to behave from the first cold morning.

The mixed-mode weeks

The hardest part of changeover is not the day you switch, but the weeks either side. In spring and autumn, a building can need heating in the morning and cooling by mid-afternoon, and different facades can need opposite things at the same time.

This is when heating and cooling fight. The usual causes are:

There is no single right deadband. Rules of thumb from controls suppliers vary, and published checklists from different countries suggest different figures. The right value depends on the building's use, the people in it and what the lease or service agreement says about temperatures. Agree it with the client and record it, rather than applying one number everywhere.

Trends to watch in the first fortnight

Changeover is a good time to set up a short list of trends and look at them a week or two later. Useful ones include:

Compare with last season's trends if you have them. Last year's data is often the best baseline you will get.

Common faults, year after year

Practice and the trade press report the same handful of changeover faults again and again:

None of these needs new equipment to fix. Most need someone to look at the right point at the right time of year.

Recording it

End each changeover visit with a short record: what was checked, what was changed (with before and after values), what is still outstanding, and what to look at next season. Keep the trends you set up. This record is what turns a changeover from a yearly scramble into a routine - and it is evidence for the client of work they would otherwise never see.

Where this fits

Seasonal commissioning is a recognised part of new building handover - BREEAM credits look for it within the first year of occupation, and the BSRIA Soft Landings framework (BG 54) builds aftercare and fine-tuning into the first years after handover. Beyond that, nothing in regulation requires it, but buildings keep changing, and the same checks keep finding the same drift.

For the wider service year, see The BMS service visit that pays for itself. The original commissioning sequence these checks build on is in Commissioning a BMS, and the energy side of setpoints, schedules and deadbands is covered in Where BMS tuning saves energy. To find what the trends are telling you, Fault detection on a BMS sets out the classic rules.

Related tools and training: the weather compensation savings, out-of-hours running cost and degree-day calculators are in tecTools, and the LTHW and CHW system commissioning courses are in tecTraining.

Published guidance mentioned: BREEAM seasonal commissioning (BRE); BSRIA BG 54/2018 Soft Landings Framework. These describe the process in their own terms - follow your project's specification and the manufacturers' instructions for any plant you work on.