Spring changeover: five things to check before the first warm week
Cooling lockouts, chillers, free cooling, deadbands and solar gain zones - five BMS checks worth making before the building needs cooling.
The first warm week of spring is when a building finds out whether its cooling is ready. If the changeover settings are wrong, the result is a run of "it is too hot" calls - or heating and cooling quietly running at the same time. A short visit before the weather turns avoids both.
1. Cooling enable and heating lockout
Check the conditions that allow cooling to run and stop heating, using the values actually in the strategy rather than the ones in the O&M manual. Overlapping lockouts let both central plants run together.
2. Chillers and heat rejection
Plant that has not run since autumn should be started and proved under the manufacturer's procedure by whoever is responsible for it. Confirm staging and rotation follow the sequence.
3. Free cooling and economisers
Prove dampers and free cooling coils move, and that the logic is in its summer state. Winter limits left in place can stop free cooling altogether.
4. The deadband between heating and cooling
Too narrow a gap between heating and cooling setpoints is the classic cause of simultaneous heating and cooling. There is no single right value - it depends on the building, its occupants and its lease - so agree it with the client and record it.
5. Solar gain zones and chilled water reset
South and west facades, atria and top floors overheat first. Check their sensors and setpoints, and make sure any chilled water reset is active rather than fixed at its coldest value.
Then set up a few trends - space temperatures, coil valve positions and chilled water delta-T - and look at them a week or two later. Our article Seasonal changeover covers the full spring and autumn lists, the mixed-mode weeks and the faults that come up every year.